Our 70-348 Managing Projects and Portfolios with Microsoft PPM Questions and Answers are an objective type study material that provides you basic and essential knowledge for passing IT certifications without wasting your precious time as well as money. From Testpassport, you can easily get the related study materials and exams notices, exams news and exam questions about 70-348 Managing Projects and Portfolios with Microsoft PPM certification. Testpassport also provides you the previous and possibly expected Questions/Answers about this certification.

When you have Testpassport Microsoft 70-348 questions and answers, it will allow you to have confidence in passing the exam the first time. In order to pass 70-348 Managing Projects and Portfolios with Microsoft PPM exam, selecting the appropriate training tools is very necessary. And professional study materials about 70-348 Managing Projects and Portfolios with Microsoft PPM exam is a very important part. Our Testpassport can have a good and quick provide of professional study materials about Microsoft certification 70-348 exam.
Share some MCP 70-348 exam questions and answers below.
You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.You have the following requirements:You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.Where should you add resources?

A. in the e-commerce portal development program project site

B. in the individual project schedules

C. in Build Team, in the e-commerce portal development program schedule

D. in the individual project sites

Answer: C

Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment, you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.You must collect information about the time that resources spend on all projects.You need to ensure that you can capture timesheet data from the existing SharePoint task lists.Which two actions will achieve the goal? Each correct answer presents a complete solution.

A. Convert the SharePoint task lists into an enterprise project.

B. Use the Get Started with Project Web App web part to add existing SharePoint task lists to Project Center.

C. Activate the enterprise project features for the SharePoint sites.

D. In Project Center, add existing SharePoint task lists to PWA as a project.

E. In SharePoint, add existing SharePoint task lists to Project Center.

Answer: A,C

You are managing an e-commerce portal development project by using Microsoft PPM.In order to communicate the status of your project to your stakeholders, you want to create a real time project status report using Microsoft Excel in Office Online Services.You need to show information about your overall project status and late tasks on your status report.What should you do?

A. From the Report tab in Project Pro for Office 365, select the In Progress | Late Tasks report. Save the report as a .pdf file to the designated reports library in PWA.

B. From the Project Details view in PWA, change the filter to the Late Tasks filter and copy and paste the tasks into Excel. Save to the designated reports library in PWA.

C. From the English folder in the PWA Data Connections library, open the OData Task Data .odc data connection file.

D. From the Power Query tab in Excel, select the From other sources | From ODBC option to add data to the report.

Answer: C

Your organization is using Microsoft PPM to manage and track all projects.The Project Management Office (PMO) needs to know which of the projects are aligned to the organization’s strategic objectives.You need to configure Microsoft PPM to use Portfolio Analysis.Which two activities should you perform? Each correct answer presents part of the solution.

A. Set up Project Departments.

B. Prioritize the drivers by specifying the priority value for each driver.

C. Configure the Full-time Equivalent calculation.

D. Define business drivers.

Answer: B,D

You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent.The IT manager adds an additional business driver that has a priority value set to 30 percent.You need to create a new prioritization that includes the additional business driver.What should you do?

A. Create a new calculated prioritization. Select the drivers to prioritize.

B. Create a new manual prioritization. Select the correct department, and then select the drivers to prioritize.

C. Create a new manual prioritization. Select the drivers to prioritize, enter the value for each driver, and then choose to normalize.

D. Create a new manual prioritization. Select the drivers to prioritize, and then rank the drivers sequentially.

Answer: C

This Microsoft MCP 70-348 real exam questions contains everything you need to pass your 70-348 exam. Although there are other Microsoft MCP 70-348 real exam questions in the market, but our products are very good, because they are updated regularly and always offer an accurate 70-348 Certification Exam Preparation. Microsoft certification offers updates to its Microsoft MCP 70-348 real exam questions absolutely free of charge. For the duration of your Microsoft MCP 70-348 real exam questions, you will get the latest and updated 70-348 Training Tools from Microsoft certification.